What is a key characteristic of the Design-Build delivery method?

Prepare for the Certified Construction Manager Test. Study with flashcards and multiple-choice questions. Each question comes with hints and explanations to boost your readiness. Ace your exam with ease!

A key characteristic of the Design-Build delivery method is that it involves a single contract for both design and construction. This integrated approach streamlines the project delivery process, allowing for better communication and collaboration between the design and construction teams. By having a unified team working under one contract, there is often an increase in efficiency, as the design and construction phases can be more closely aligned. This can lead to a reduction in project timelines and cost overruns, as issues can be identified and addressed more swiftly. The Design-Build method contrasts with traditional delivery methods, where separate contracts are needed for design and construction, potentially leading to miscommunication and conflicts.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy