What is a key feature of the CMAA Agency CM at Risk Contract?

Prepare for the Certified Construction Manager Test. Study with flashcards and multiple-choice questions. Each question comes with hints and explanations to boost your readiness. Ace your exam with ease!

A key feature of the CMAA Agency CM at Risk Contract is that the Construction Manager (CM) provides extensive professional services during the design phase of the project. This involvement is crucial as it allows the CM to collaborate closely with the owner and the designer, enabling them to influence project decisions early on and improve cost estimates, scheduling, and overall project efficiency. By being actively engaged during the design stage, the CM can offer valuable insights and recommendations that can help avoid potential conflicts and costly changes during construction. This proactive approach not only enhances the project’s likelihood of success but also helps in refining the Guaranteed Maximum Price (GMP), which is a central component of this contract structure.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy